Tell us what you think and help shape your community

Take part in consultations, surveys and conversations that interest you, and find out more about decisions we’ve made

 

 

 

 

 

Have your say

Current opportunities to get involved

Transport Master Plan - Phase 1 feedback survey

This is an example activity for demonstration purposes only. This site is operated by Delib Ltd and submitted responses will be discarded. We want your views on how increasing the number of buses on our roads is working. Increasing the amount of buses running across the city is part of Phase 1 of the Arlen City Transport Master Plan. The Master Plan aims to overhaul the city’s public transport, make it much easier to get around on foot or by bike, and reduce the need to...

TRO 1002 - Mina Road - Proposed double yellow lines

This is an example activity for demonstration purposes only. This site is operated by Delib Ltd and submitted responses will be discarded. Concerns have been raised about inconsiderate and obstructive parking along Mina road. This reduces visibility and access for drivers and pedestrians. To address this issue, it is therefore proposed to introduce ‘No Waiting At Any Time’ restrictions (Double Yellow Lines) south of the junction with Watercress road.

Closed consultations and engagement

Issues we asked you about previously

Transport Master Plan initial consultation

This is an example activity for demonstration purposes only. This site is operated by Delib Ltd and submitted responses will be discarded. We are planning a new Transport Master Plan and we would like to hear from residents of Arlen Hill. The Transport Master Plan will be a long term project that upgrades the public transport system with the intention of making travel easier and more sustainable for everyone. Let us know what you think of the plan and which areas you think need...

Bus route consultation

This is an example activity for demonstration purposes only. This site is operated by Delib Ltd and submitted responses will be discarded. Feedback from the initial Transport Master Plan consultation showed that residents of Arlen Hill mostly require more bus routes, servicing different areas of Arlen Hill. As a result of this we have decided to make this the first phase of the plan. We will be introducing new services across the district, but we need to find out where they would be...

Smallville local centre: conversion of on-street parking spaces

In 2020, an area of on-street parking was suspended on Smallville High Street to enable social distancing and queuing. Now Covid restrictions have been lifted we would like to know if residents would like us to permanently remove the former areas of on-street parking that were suspended on the High Street in 2020 and widen the footway in these areas.

Your impact

Issues we have consulted on and their outcomes See all outcomes.

We asked

We asked for views on 6 proposed traffic calming measures along Arlen Road, Smallville. The measures aimed to reduce vehicle speeds, reduce ‘rat-running’ and improve pedestrian safety. The consultation ran from 17 August to 16 September 2022.

You said

We received 148 responses to the consultation.
Respondents to the online survey were asked whether they supported or opposed the 6 traffic calming proposals:

  • two raised tables on Arlen Road: 76% supported, 20% opposed
  • adding extra speed cameras: 65% supported, 31% opposed
  • introducing 20mph speed limits: 53% supported, 22% opposed
  • use of street print coloured textured surfacing: 67% supported, 11% opposed
  • introducing a pedestrian only zone: 60% supported, 11% opposed
  • double yellow lines on London Road: 78% supported, 10% opposed

We did

There have been no significant changes to the proposed designs for zones 2, 3 and 4.
We have heard views on future phases of traffic calming, particularly in zones 1 and 5 where you enter Smallville. Where possible, we will try to introduce some of these measures earlier than planned.

The project team will:

  • complete a detailed design for the scheme, following public feedback
  • proceed with the construction of the Smallville traffic calming scheme
     